Timeline

  • Timeline item 1 - complete

    Phase 1

    Stakeholder Engagement Plan

    Completed 2019

  • Timeline item 2 - complete

    Phase 2

    Our Coast Our Future - Project Scoping Report

    Completed 2019

  • Timeline item 3 - complete

    Phase 3

    Coastal Hazard Mapping

    June 2020

    Our Coast Our Future Engagement Portal Launch

    22 April 2020

    Threats & Values Survey

    22 April 2020

    Community Online Engagement Sessions

    Introduction to Our Coast Our Future

    25 May 2020

  • Timeline item 4 - complete

    Phase 4

    Identify key assets potentially impacted

    August 2020

  • Timeline item 5 - complete

    Phase 5

    Undertake a risk assessment of key assets in coastal hazard areas

    August 2020

    Community Online Engagement Sessions

    Assets at risk and adaptation options

    2 August 2020

  • Timeline item 6 - complete

    Phase 6

    Identify potential adaptation options

    August 2020

  • Timeline item 7 - complete

    Phase 7

    Adaptation Options Evaluation

    September 2020

  • Timeline item 8 - complete

    Phase 8

    Our Coast Our Future Strategy Finalisation

    31 October 2020

  • Timeline item 9 - complete

    Implementation Phase