Urban Play will be undertaking the 20/21 Playground Replacement Program within the Gladstone Region. Works include the design and construction of four (4) playgrounds and upgrades to three (3) playgrounds within our Region.

Memorial Park - Gladstone

Upgrade Traverse Climbing Wall

10 May – 18 May 2021

  • Site Establishment
  • Remove Existing Climbing Cleats
  • Clean, Prep & Repaint Climbing Wall
  • Install New Climbing Cleats
  • Removal of Existing Bark Softfall
  • Supply & Install New Bark Softfall
  • Removal of Existing Climbing Wall Signage
  • Supply & Install New Climbing Wall Signage
  • Site Clean / Remediation Works
  • Practical Completion Inspection

Bunting Park – Calliope

Old Basketball Court (Area 1)

13 – 21 May 2021

  • Site Establishment
  • Demo of Old bitumen Basketball Court
  • Supply & Install Topsoil
  • Supply & Install Turf
  • Site Clean / Remediation Works
  • Practical Completion Inspection

Bunting Park – Calliope

Corocord Net Area & Basket Swing (Area 2)

24 May – 31 May 2021

  • Site Establishment
  • Removal of Existing Corocord Net & Sand Softfall
  • Supply & Install New Playground Equipment
  • Supply & Install New Sand Softfall
  • Removal of existing Basket Swing & Bark Softfall
  • Supply & Install New Basket Swing & Bark Softfall
  • Site Clean / Remediation Works
  • Practical Completion Inspection

Turkey Beach Park – Turkey Beach

18 – 24 May 2021

Playground Upgrade

  • Site Establishment
  • Removal of Existing High Profile Concrete Kerb
  • Prep & Install New High Profile Concrete Kerb
  • Removal of Existing Sand
  • Supply & Install New Sand Softfall
  • Site Clean / Remediation Works
  • Practical Completion Inspection

Air Sea Rescue Park – Seventeen Seventy

31 May – 7 June 2021

Playground Replacement

  • Site Establishment
  • Removal of Existing Playground Equipment, Fencing & Sand Softfall
  • Supply & Install New Playground Equipment
  • Supply & Install New Sand Softfall
  • Supply & Install New Fencing
  • Site Clean / Remediation Works
  • Practical Completion Inspection

Goonananga Park – Gladstone

7 June – 14 June 2021

Playground Replacement

  • Site Establishment
  • Removal of Existing Playground Equipment, Kerbing & Bark Softfall
  • Supply & Install New Playground Equipment
  • Supply & Install New Kerbing
  • Supply & Install New Bark Softfall
  • Site Clean / Remediation Works
  • Practical Completion Inspection

Toonee Park - Gladstone

14 June – 21 June 2021

Playground Replacement

  • Site Establishment
  • Removal of Existing Playground Equipment, Kerbing & Rubber Softfall
  • Supply & Install New Playground Equipment
  • Supply & Install New Kerbing
  • Supply & Install New Sand Softfall
  • Site Clean / Remediation Works
  • Practical Completion Inspection

Frank & Francie Hart Park – Curtis Island

18 June – 28 June 2021

Playground Replacement

  • Site Establishment
  • Removal of Existing Playground Equipment, Kerbing & Bark Softfall
  • Supply & Install New Playground Equipment
  • Supply & Install New Kerbing
  • Supply & Install New Bark Softfall
  • Site Clean / Remediation Works
  • Practical Completion Inspection

Commencement dates have been confirmed, with an expected completion date of Monday 28 June, weather permitting.